Changes to pedestrian and cycling routes at the southern end of Hatanpään valtatie

Construction of municipal infrastructure continues throughout the summer at the southern end of Hatanpään valtatie. Starting on Monday 3 June, the work area will expand on the west side of the...

Read more

Water supply work to begin on Lentokonetehtaankatu in week 21

We will begin water supply construction work in front of Lentokonetehtaankatu 5 this week (week 21). Due to the work, an excavation will be made on the east side of the property, and the access route...

Read more

One lane in each direction on Hatanpään Valtatie from week 20

Municipal infrastructure works are progressing at the southern end of Hatanpään Valtatie. In week 20, the work area will expand to the eastern side of Hatanpään Valtatie between Hatanpään...

Read more

More single-lane road sections on Hatanpään Valtatie during week 14

Municipal infrastructure work is progressing in the southern part of Hatanpään Valtatie. The work area will expand to the western side of Hatanpään Valtatie between Vihilahdenkatu and...

Read more

Tramway Modification Work to Begin at the Eastern End of Lääkärintie in Week 10

The Pirkkala-Linnainmaa Alliance of Tampere Tramway will carry out tramway modification work at the eastern end of Lääkärintie, at the current endpoint of the tramway track, during the spring. The...